To further enhance a healthy and safe environment within the compound of its newly-rehabilitated and recently energized Cubi Substation, Subic EnerZone launched various projects last March 14.
Projects included the following: a.) re-modeling of the existing perimeter fence, b.) construction of retaining wall, c.) a new service road, d.) re-painting of the switch gear building, and e.) a drainage system.
For the perimeter fence, the color scheme was defined from SEZ's logo. And while the bright colors identifies SEZ, it also serves as an early warning device to all motorists passing by the accident-prone area.
The main purpose in constructing the retaining wall is to control the soft soil from a mountain slope in the area from eroding.
Meanwhile, the new service road is an 18 x 6 meter wide road to be used as an access road for maintenance servicing.
The existing transformers and switch gears, which were all non-operational, were transferred to the Procurement and Property Management Department (PPMD) of the Subic Bay Metropolitan Authority (SBMA) by the Aboitiz Projects group.
|